Cochranton library board looks to cut future costs on new building

COCHRANTON — The Cochranton Area Public Library Board of Trustees may look to cut potential future costs on the new library building, slated for construction behind the current location, for which they’ve recently opened bids.

Trustees discussed Phase 1 project bids at a special meeting Tuesday night, reviewing estimates and planning further discussion tonight with a representative of New York-based architectural firm Clark Patterson Lee.

Approximate main bids received include $570,233.35 from Roche Builders, $526,858 from Hill Construction, $591,086 from Norbert B. Miller Construction and $514,000 from Bernarding’s Builders, all based in Cochranton.

Bids will hold for 180 days, according to Nadena Kramer, library director, and include alternate costs for additional features, including a lift mechanism for cleaning and bulb replacement of a large foyer light and exterior pole-mounted light sighting and wiring installation; and performance and payment bonds regarding material and labor costs.

“The builders are well-respected people in the community,” Kramer said. “They have good reputations.”

Trustees said that each of the bids came in relatively over budget based on current architectural plans and compared to an approximate $400,000 cap for which they initially planned, according to Joan Kardos, treasurer.

“I was sure we’d be in the $400,000 category,” she said, claiming the board was clear on affordability with its project affiliates prior to the bidding stage.

Trustees mentioned reviewing and possibly altering the current architectural designs to see where they can cut costs.

“Contractors all say they can find ways to trim the fat once their bid is chosen,” she said. “They’re all willing to discuss the project.”

Certain changes have already been made to design plans regarding the roof shape, potential attic space and pillar structures, according to Susan Armburger, board president.

Phase 1 bids do not include cabinetry, shelving or any Phase 2 work, which includes demolition of the current building, parking lot paving and landscaping, Kramer said.

“The old building is in rather poor health,” she added, mentioning an ongoing leak, ice dam issue and high seasonal utility costs. “This building has to come down or there will be no parking lot for the next one.”

The board of trustees made no final decisions as of their Tuesday meeting and reserve the right to accept or reject any bid approximately within the next six months.

1
Text Only
Local News
Business Marquee
AP Video
Dempsey: Putin May Light Fire and Lose Control In Case of Fire, Oxygen Masks for Pets Mobile App Gives Tour of Battle of Atlanta Sites Anti-violence Advocate Killed, but Not Silenced. Crashed Air Algerie Plane Found in Mali Arizona Prison Chief: Execution Wasn't Botched Calif. Police Investigate Peacock Shooting Death Raw: Protesters, Soldiers Clash in West Bank Police: Doctor Who Shot Gunman 'Saved Lives' 'Modern Family' Star on Gay Athletes Coming Out MN Twins Debut Beer Vending Machine DA: Pa. Doctor Fired Back at Hospital Gunman Raw: Iowa Police Dash Cam Shows Wild Chase Obama Seeks Limits on US Company Mergers Abroad Large Family to Share NJ Lottery Winnings U.S. Flights to Israel Resume After Ban Lifted Official: Air Algerie Flight 'probably Crashed' TSA Administrator on Politics and Flight Bans Raw: National Guard Helps Battle WA Wildfires Raw: Ukraine's Donetsk Residents Flee
Hyperlocal Search
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Stocks